INSTALLATION OF QSB

Steel structure erection and erection process is the last step in the process of building pre-engineered steel buildings – “Design – Manufacturing – Erection”. In this step, all the components will be gathered at the factory to the site, the components are connected together through high strength bolt connection.

[/col]
[col span=”4″ span__sm=”12″]

After the design and manufacturing phase at QSB factory is the erection phase at the project. Construction and erection can be divided into 5 stages: Positioning anchor bolts. Erection of trusses, roofing roofs, walls and finishing Acceptance and handover of works and put into use Maintenance – Warranty works During the erection process, there must be temporary bracing. Use roof purlins, wall purlins combined with working bracing cables to fix and link trusses together。

[/col]
[col span=”4″ span__sm=”12″]

When completing the cover: regularly use chalk or string tension to locate or mark the landmark positions to weigh the sheets. When walking on the roof, you must put your foot on the lower wave (sound wave), if you step on the high wave, it will crush the tole zone, which can cause dents or punctures causing leaks. Do not walk up the bright tole sheets.

[/col]

[/row]

[/section]
[section bg_color=”rgb(246, 246, 246)” border=”1px 0px 0px 0px” border_color=”rgba(0, 0, 0, 0.05)”]

[row]

[col span=”4″ span__sm=”12″]

[featured_box img=”21036″ img_width=”92″ pos=”left” margin=”px px px px” icon_border=”2″ icon_color=”rgb(143, 232, 127)”]

Accurate progress

Progress is always a big concern of QSB, creating QSB’s position in the market.

[/featured_box]

[/col]
[col span=”4″ span__sm=”12″]

[featured_box img=”21034″ img_width=”92″ pos=”left” margin=”px px px px” icon_border=”2″ icon_color=”rgb(143, 232, 127)”]

Best quality

Quality is highly appreciated by QSB’s customers.

[/featured_box]

[/col]
[col span=”4″ span__sm=”12″]

[featured_box img=”21035″ img_width=”92″ pos=”left” margin=”px px px px” icon_border=”2″ icon_color=”rgb(143, 232, 127)”]

Cost savings

Always have the best, economical solutions for customers.

[/featured_box]

[/col]

[/row]
[title style=”center” text=”INSTALLATION PROCESS”]

[row label=”STEP 1″]

[col span=”4″ span__sm=”12″]

[ux_image id=”21277″]

[/col]
[col span=”4″ span__sm=”12″]

PRIORITY Step: Prepare for erection.

Check erection equipment, erection materials: quantity, safety, quality of materials …

Step 1: Locate the anchor bolts.

[/col]
[col span=”4″ span__sm=”12″]

[ux_image id=”21267″]

[/col]

[/row]
[row label=”STEP 2″]

[col span=”8″ span__sm=”12″]

[ux_image id=”21842″ image_size=”large”]

[/col]
[col span=”4″ span__sm=”12″]

Step 2: TRANSPORT MATERIALS TO THE WORKS.

Receiving steel structure goods from the factory, life-saving cables, installation tools and equipment lifeline, ty, cables, link bolts, purlins, corrugated iron, …

[ux_image id=”21830″]

Step 3: Installation of steel columns.

[/col]

[/row]
[row label=”STEP 3″]

[col span=”6″ span__sm=”12″]

[ux_image_box img=”21768″]

Step 4: Combination of steel trusses at the ground.

[/ux_image_box]

[/col]
[col span=”6″ span__sm=”12″]

[ux_image_box img=”21751″]

Step 5: Install steel truss.

[/ux_image_box]

[/col]

[/row]
[row label=”STEP 4″]

[col span=”4″ span__sm=”12″]

Step 6: Install the next rafter.

Step 7: Installation of purlin.

Installation of steel truss roof purlins (50%), wall purlins (50%) bracing columns, bracing along trusses, columns…

[ux_image id=”21187″]

[/col]
[col span=”8″ span__sm=”12″]

[ux_image id=”21442″]

[/col]

[/row]
[row label=”STEP 5″]

[col span=”4″ span__sm=”12″]

Step 8: Continue to install steel rafters and bracing purlins, bracing EB until the entire frame is completed.

[ux_image id=”21791″]

[/col]
[col span=”4″ span__sm=”12″]

Step 9: Complete purlins, wall purlins, bracing ties, bracing system.

 

[ux_image id=”21389″]

[/col]
[col span=”4″ span__sm=”12″]

Step 10: Roofing, gutters, corrugated iron walls.

 

[ux_image id=”21458″]

[/col]

[/row]
[row label=”STEP 6″]

[col span=”2″ span__sm=”12″]

Step 11: Completion.

[/col]
[col span=”5″ span__sm=”12″]

[ux_image id=”21344″]

[/col]
[col span=”5″ span__sm=”12″]

[ux_image id=”21239″]

[/col]

[/row]

[/section]
[section bg_color=”rgb(244, 244, 244)”]

[row]

[col span__sm=”12″]

[title style=”bold-center” text=”PRINCIPLES OF INSTALLATION”]

[row_inner]

[col_inner span=”4″ span__sm=”12″]

quality assurance

+ Erection of columns with purlins (if any) tie the columns together. Alignment column is finished neatly, then proceed to erect the truss.
+ Install the truss frame inside and then install the outside truss frame (according to the moving path of the crane – see attached construction organization drawing)
+ The erection must be started in the space with the wind bracing (column and roof bracing).

[/col_inner]
[col_inner span=”4″ span__sm=”12″]

ENSURING SAFETY

+ Fix the two erection brackets in the wind-bracing position before mounting the adjacent bracket. This process is then progressed to the next frames.

+ In the erection process, there must be temporary bracing. Use roof purlins, wall purlins combined with working bracing cables to position and link trusses together.

+ Install tole after aligning truss frame, straight purlin, clean cleaning, complete paint scratches on truss and purlin.

[/col_inner]
[col_inner span=”4″ span__sm=”12″]

ASSURANCE OF PROFESSIONALISM

+ When completing the cover: regularly use chalk or string tension to locate or mark the landmark positions to weigh the sheets.

+ When walking on the roof, you must put your foot on the lower wave (sound wave), if you step on the high wave, it will crush the tole zone, which can cause dents or punctures causing leaks.

+ Do not walk up the bright tole sheets

[/col_inner]

[/row_inner]
[gap height=”36px”]

[title style=”bold-center” text=”CUSTOMER REVIEWS”]

[ux_slider nav_pos=”outside” nav_style=”simple” nav_color=”dark”]

[row_inner]

[col_inner span=”4″ span__sm=”12″]

[testimonial image=”3833″ name=”TIEN River highlights”]

The highlight of Tien River is pride here. Thank you QSB, the steel structure is so beautiful…

[/testimonial]

[/col_inner]
[col_inner span=”4″ span__sm=”12″]

[testimonial image=”3833″ name=”Dau Tieng Project”]

Excellent progress, quality, cost, nothing to criticize ….

[/testimonial]

[/col_inner]
[col_inner span=”4″ span__sm=”12″]

[testimonial image=”3833″ name=”Spring Garden”]

I must say that they enjoy working with QSB Steel, They work very professionally …

[/testimonial]

[/col_inner]

[/row_inner]

[/ux_slider]
[title style=”bold-center” text=”QSB STEEL PROJECT”]

[blog_posts columns=”3″ depth=”1″ slider_nav_style=”simple” slider_nav_position=”outside” cat=”1″ posts=”5″ image_height=”180px” image_size=”large”]

[/col]

[/row]

[/section]